if 12 men can paint a building in 20 days, how long will it take 15 men to finish the same job?
Answers
Answered by
1
Answer:
I think 16 days
I just think because I m not good in maths
Answered by
2
Answer:
days needed by 12 men to complete the wall=20
Days needed by 1 men to complete it= 20×12
days needed by 15 men to finish the same wall=20×12÷15
=16 Days(answer)