Math, asked by adrianecoc2004, 2 months ago

if 12 men can sew 100 shirt in 5 days, how long will it take 15 men to sew the 100 shirt

Answers

Answered by Farhan5555
1

Answer:

4 Days

Step-by-step explanation:

We can simply use the formula,

 \frac{m1 \times d1 \times t1}{w1} =  \frac{m2 \times d2 \times t2}{w2}

Where, m is number of men(or the workers), d is number of days, t is amount of time they work for each day, w is amount of work given.

Since the amount of time spent is same in both cases, t is constant.

Let the number of days taken by 15 men to complete the work be x.

=>12×5×t/100=15×x×t/100

=>12×5=15×x

=>x=4 Days