Math, asked by samarjit101, 7 months ago


If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men
and 8 women complete the same work?​

Answers

Answered by sahilwar75
1

Answer:

it can not done because it has already done

Answered by gandiharini2007
4

Answer:

12 men

= 18 women

∴ 4 m = (18/12) × 4

= 6 women

Total women in second case = 4 men + 8 women

6 + 8 = 14 women

18 women can do a piece of work in 7 days

Let 14 women will do the same work in x days

∴ 18 : 14 :: 7 : x

(less women, more days)

⇒ 18 : 14 :: x : 7

(Using inverse proportion)

X = (18 × 7)/14

= 9

∴ They will complete the work in 9 days

Step-by-step explanation:

Hope it helps u