If 12 men work 8 hours a day to complete a work in ten days, how many men working 12 hours a days can complete the work in 5 days
Answers
Answered by
3
Pls mark this as the brainliest answer
Attachments:
Answered by
2
Answer: 16 men
Step-by-step explanation:
From the text, we know that =
men : hours : days
12 : 8 : 10
https://www.quora.com/12-men-work-8-hours-per-day-to-complete-the-work-in-10-days-To-complete-the-same-work-in-8-days-working-15-hours-a-day-how-many-men-are-required
M1 x D1 x H1 = M2 x D2 x H2
12 x 8 x 10 = a x 12 x 5
a = 16
So, 16 men are needed