Math, asked by anilkrsingh3138, 8 months ago

if 12 person can do the work in 15 days . in how many days same work be completed by 20 person​

Answers

Answered by Anonymous
21

Answer

25 days

Solution

Given

12 person can do work in 15 days

1 person can do the work in 15/12 days

or 5/4 days

Apply unitary method

Days required by 1 person to do the work = 5/4

∴ Days required by 20 person = 5/4 × 20 days

=> 5 × 5 days

=> 25 days

Answered by sousek
1
12 persons = 15 days
20 persons = ? days
This is in direct proportion which means
X1/y1 =x2/y2
So here x1 =12 persons
Y1 = 15 days
X2 = 20 persons
Y2 =?
We need to find y2
By cross multiplication
12/15 =y2/20
15 x20/12 x y2
= 25 days



Hope this helps !