Math, asked by kamalbamma, 9 months ago

If 12 persons can complete a work in 4 days in how many days can 8 person complete that work

Answers

Answered by Anonymous
4

8 person complete that work in

 = 4 \times  \frac{12}{8}  \\  = 6 \:  \: days

Answered by Anonymous
0

Answer:

→ 8 person complete that work in

\huge\begin{lgathered}= 4 \times \frac{12}{8} \\ = 6 \: \: Days\end{lgathered}