Math, asked by radheakhanibo100, 3 months ago


if 12 persons can do 3/5 of certain work in 10 days,then how many persons are required to finish the whole work in 20?​

Answers

Answered by palak828069
1

Work=No. Of Men * Days

3/5 part of work= 12*10=120 units

=> Whole work= 120/3*5= 200 units

So ATQ, men required to complete 200 units of work in 20 days are 200/20 = 10 men

I hope it's helpful for you