if 12 workers take 70 day to complete one work how many days will 21 workers take to complete the same work
Answers
Answered by
12
Given:-
- 12 workers take 70 days to complete one work.
To Find:-
- In how many days will 21 workers complete the same work =?
Solution:-
Hence, 21 workers complete a work in days.
Answered by
16
Solution :-
Let the Required Number of Days be x.
Then, we have the Following Table :
Clearly, More Men will take Less Days to Finish the Work.
So, it is a Case of Inverse Proportion.
∴ The 21 Workers would take 40 Days to Complete the Work . . .
Additional Information :-
Inverse Proportion :- Two Quantities x and y are said to be in Inverse Proportion if xy = k, where k is a Constant.
Thus,
Similar questions