If 12 workers working 6 hours a day can finish work in 14 days, then the number of workers required to
finish the same work in 8 days for 7 hours a day is
a) 24
b) 36
d) 18
c) 12
Answers
Answered by
0
Answer:
the worker required for to work in 8dys is 24 worker
Answered by
5
Answer:
18
Step-by-step explanation:
workers. 12. x
time(in hours) 84 56
let x be required workers
12÷84 =x÷56
12×84 =x×56
x=12×84/56= 18