if 12men or 18women can complete the work in 7 days. In how many days can 4 men or8 women complete the same work . do in full process
Answers
Answered by
2
9 DAYS
12 men
= 18 women
4 m = (18/12) × 4
= 6 women
Total women in second case = 4 men + 8 women
6 + 8 = 14 women
18 women can do a piece of work in 7 days
Let 14 women will do the same work in x days
18 : 14 :: 7 : x
(less women, more days)
18 : 14 :: x : 7
(Using inverse proportion)
X = (18 × 7)/14
= 9
They will complete the work in 9 days