Math, asked by badydoll6647, 1 year ago

If 13 men can do a piece of work in 140 days in how many days 28 men will do it how many mens they will be required to complete the work in 35 days

Answers

Answered by vrutant4
2

13 ----> 140 days

28----> x days

X days =140 *28/13

Hence 30.1 days will be required