If 13 men can do a piececpf work in 140 days In how many days 28 men will do it How many men will be required to complete work in 35 days in direct or inverse variation
Answers
Answered by
1
One man will do the same amount of work in 13*140 = 1820 days
So 28 men will do it in 1820/28 = 65 days
So 28 men will do it in 1820/28 = 65 days