Math, asked by IrabanBhattacharya14, 2 months ago

If 14 men can complete a work in 7 days, then how many more men

required to complete the same work in 1 day?​

Answers

Answered by vaibhaviyjagtap2904
1

Answer:

7

Step-by-step explanation:

just 7 people required

Answered by iVxsoz
2

Your answer would be 84.

Amount of men=14

Can complete in=7 days

What we need to find=How many more men  required to complete the same work in 1 day

The first step is to multiply 14 by 7. After this, we get 98. But it says how many MORE. So we need to subtract. 98-14=84.

Thus, your answer is 84. I hope this helped you.