If 14 men can do a piece of work in 3 days, in how many days can 6 men do the same work?
Answers
Answered by
0
Answer:
7 days
Step-by-step explanation:
please make it brainliest answerand follow me
Answered by
0
Answer:
14 men = 3 days
1 man = 3 * 14 = 42 days
6 men = 42/6 = 7days