if 15 men can build a wall in 48 hours , how many men will be required to do the same work in 30 hours​

Answers

Answered by Ananya1514
2

Answer:

Step-by-step explanation:

It is given that the 15 workers can build a wall in 48 hours.

Let x workers can complete the same work in 30 hours.

Divide both sides by 30.

The value of x is 24.

Therefore, 24 workers can complete the same work in 30 hours.