if 15 men can complete 1/4 of work in 10 days how many more men should be employed to finish the rest of the work in 30 days

Answers

Answered by ravi4114
0
Since, if 15 men do 1/4 of work in 10 day
So, 1 man can do this work in x days
x=15/10 =2/3
Now, no of men do this work in 30 days = 2/3*30=45 men ans