Math, asked by divyanshshankhdhar, 10 months ago

If 15 men can complete a piece of work in 30
days, in how many days will 18 men complete
it?​

Answers

Answered by indumalik2255
1

Answer:

x=15×18/30

x=9

Please follow me mate.

It's a humble request mate.

Answered by Anonymous
0

ANSWER:-

Given:

If 15 men can complete a piece of work in 30 days.

To find:

How many days will 18 men Complete it.

Solution:

Given,

⏺️M1= 15

⏺️M2= 18

⏺️D1= 30

⏺️D2= ?

⏺️W1 = 1

⏺️W2= 1

Using the formula;

M1D1W2 = M2D2W1

=) 15×30×1 = 18× D2× 1

=) D2= 15× 30/18

=) D2= 450/18

=) D2= 25 days

Hence,

25 days will 18 men completed it.

Hope it helps ☺️

Similar questions