Math, asked by anirudha2255, 4 months ago

If 15 men can complete a piece of work in 30 days, in how many days will 18 men
complete ?​

Answers

Answered by Pratikshamane0604
1

answers is 25 days

solutions=

15 men can finish a piece of work= 30 days

1 man can finish a piece of work= 30 x 15= 450

18 men can finish a piece of work= 450/18= 25

ANS= 18 men can finish a piece of work in 25 days.