If 15 men can complete a piece of work in 30 days,in how many days will 18 men complete it?
Answers
Answered by
23
18:30::15:x
➦ 18 × x = 15 × 30
➦ x =
➦ x = 25
Hence , 18 mens can complete the work in 25 days .