If 15 men can complete a piece of work in 30 days,in how many days will 18 men complete it?
Answers
Answered by
5
Answer:
hope it help pls mark me as a brainlist
Step-by-step explanation:
Since 15 men can complete a piece of work in = 30 days
∴ 1 man can do the work in =30 × 15 days
∴ 18 men can do the work in = (30 × 15)/18 = (5 × 15)/3
= 5 × 5 = 25 days
Hence 18 men can do the work in 25 days.
Answered by
28
18:30::15:x
➦ 18 × x = 15 × 30
➦ x =
➦ x = 25
Hence , 18 mens can complete the work in 25 days .