If 15 men can do a piece of work in 14 days , in how many days can 7 men do it?
Answers
Answered by
2
Step-by-step explanation:
7*14÷ 15 =6.5333444
so And is 7 days
Answered by
4
Answer:
30 days
Step-by-step explanation:
14*15/7=30
hence 7 men will do the same work in 30 days