If 15 men can do a piece of work in 3 days then 9 men will do it ​

Answers

Answered by Anonymous
22

Answer:

 = 15 \: men \: can \: do \: a \: piece \: of \: work \: in \: 3 \: days \\  = 1 \: man \:   =  \frac{3}{15}  \\ 9 \: men =  \frac{3}{15}  \times 9 \\  \\  =  \frac{27}{15}  \\  =  \frac{9}{5}  \: days

Answered by Anonymous
10

Answer:

GIVEN-

➡Number of days taken by 15 men=3 days

➡Number of days taken by 9 men= 'x' days

Step-by-step explanation:

SOLUTION-

\bold\red{less\:men➡more\:days}

\bold\green{◀Inverse\:Variation▶}

15 \times 3 = 9 \times x \\  = x =  \frac{15 \times 3}{9}  \\  \\  = x =  \frac{5 \times 3}{3}  \\  \\  = x =  5

So, 9 men will take 5 days to complete a piece of work.