If 15 men can level a ground in 60 days, in how many days can 36 men level the same ground?​

Answers

Answered by GaneshRM2006
4

Answer:

if 15 men can level a ground in 60 days

1 man can do it in 15×60 = 900

1 man can do 1/900 of the total work in one day

36 men can do 36/900 of work in one day

it would take 900/36 = 25 days to complete the work

             