if 15 men can paint school in 7 days how many more men are required to complete the same in 3 days
Answers
Answered by
1
Answer:
The ans is 12
thank you
☺️
Answered by
4
Answer:
No. of men is inversely proportional to number of days.
We know, if x is inversely proportional to y,
x1 y1 = x2 y2
Here, x1=15 men, y1=7 days, x2= 'x' men, y2=3 days
Applying the formula,
15 * 7 = x * 3
Or x = 5 * 7 = 35 men
Therefore, number of more men = 35-15 = 20 more men.