If 15 men can repair a road in 24 days, then how long will take in nine men to repair the same road ?
Answers
Answered by
19
Answer:
40days
Step-by-step explanation:
1 man can do the work in days=15×24=360days
Then 9men can do the work in days=360/9=40days