)If 15 men can repair a road in 24 days . then how long will it take 9 men to repair the same road ?

Answers

Answered by Anonymous
5

Answer:

40 days.

15*24/9 = 40 days

I hope it help you...

Answered by arunabalamohapatra
3

Answer:

40 day's.............