If 15 men complets the work in 5 days then how much time wil 8 men takes to complete the work
Answers
Answered by
1
Given , 15 men complete work in 5 days
lets consider 15 men work for 1 day & each men do 1 work (consider they are making chairs)
so,
1 day work =15 chairs
5 day work =15 * 5=75 chairs
we get ,
total work =75 chairs
to find days required when 8 men are working..
75/8 = 9(3/8) days