Math, asked by birk4190owpxkt, 1 year ago

if 15 men working 6 hours per day can complete a piece of work in 16 days in how many days will 10 men complete the same work by working 8 hours a day?

Answers

Answered by Khushi020
13
Ist case:
No. of men =( No. of men given ) × (No. of days) =15×16 =240
No. of hours =6

IInd case:
Let no. of days be x
No. of men =( No. of men given ) × (No. of days) =x×10 =10x
No. of hours =8

No. of men =240 & 10x
No. of hours = 6 & 8

In Inverse variation xy =k,
240 × 6 = 10x × 8
1440/8 = 10x
180 = 10x
180/10 = x
18 = x


Thus,
No. of days is 18


HOPE IT WILL HELP U..