Math, asked by rajnisharma131117, 8 months ago

if 15 men working 6hour per day can complete a piece of work in 16 days .in how many days , will 10 men complete the same work by working 8 hours a day?​

Answers

Answered by 19PRESA0041
1

No They will complete the work in 18 days.

Similar questions