If 15 men working a 9 hours a day can reap a field in 16 days , then in how many days will 18 men reap the field working 8 hours a day.
Answers
Answered by
7
15 men= 9 hours a day= reap=16 days
18 men= 8 hours a day=reap=?
Plz see this picture I have done this question before on notes so I just screenshot it.
So this is ur answer!
Plz mark as brainliest.
Regards,
Navyatuli44
Attachments:
Answered by
11
Answer:
15 days will be required for 18 men to reap the field working 8 hours a day
Step-by-step explanation:
Given that 15 men working 9 hours a day can reap a field in 16 days
Total work
Let 18 men can working 8 hours a day can reap a field in days
Total work
Work is same, thus we get
Hence, 15 days will be required for 18 men to reap the field working 8 hours a day