If 15 workers can finish a task in 42 hours, calculate the number of workers required to complete the same task in 30 hours.
Answers
Answered by
3
Answer:
21 workers required complete the task
Step-by-step explanation:
15 workers can finish a task in 42 hours
workers required to complete the same task in 30 hours is
15*42/30
= 21 workers
21 workers required complete the task
Answered by
3
15 workers can finish a task in 42 hours
workers required to complete the same task in 30 hours is
15*42/30
= 21 workers
21 workers required complete the task