If 15 workers can finish a task
in 42 hours, calculate the
number of workers required to
complete the same task in 30
hours. *
O 24
O 21
O 20
O 26
Answers
Answered by
4
Answer:
24
Step-by-step explanation:
If 15 workers can finish a task
in 42 hours, calculate the
number of workers required to
complete the same task in 30
hours. *
O 24 ✔✔✔
O 21
O 20
O 26
Answered by
0
Answer:
the answer is 24for this