. If 15 workers can finish a task in 42 hours, calculate the number of workers required to complete the same task in 30 hours.

Answers

Answered by singhajaypratap071
3

Answer:

21 is the correct answer

thank you

Answered by Anonymous
2

 \huge{ \red { \fbox{answer}}}

 =  > 15 : 42 = x : 30 \\  \\  =  > 15 \times 4 2= x \times 30 \\  \\  =  > x =  \frac{360}{30}  \\  \\  =  > x = 21

  • 21 workers is the answer

hope this helps!!