if 15 workers can finish a task in 42 hours calculate the number of workers required to complete the task in 30 hours​

Answers

Answered by thesundram2004
0

Answer:

630

Step-by-step explanation:

they are inversely proportional. Now, assume that the number of workers required to complete the task in 30 hours be “x”. => C = 15 × 42 = 630. So, the number of 21 workers are required to complete the task in 30 hours.

Answered by prathamkundu1
0

Answer:

21 workers

Step-by-step explanation:

when, 42 hours need to do a task for 15 workers

1 hours need to do a task for 15/42 workers

30 hoires need to do a task for 15/42*30

=21 works.