If 15 workers could finish the work in 42 hours how many workers are required to finish the same work in 30 hours
Answers
Answered by
1
Answer:
21 is the write answer of the question
Answered by
1
Number of workers = C/hours (here “C” is the constant of proportionality)
Now, consider the first case: “15 workers can finish a task in 42 hours”
Here, 15 = C/42
=> C = 15 × 42 = 630.
Now, consider the second case: “x workers can finish a task in 30 hours”
Here, x = C/30
=> x = 630/30