If 15 workers take 60 days to complete one task how many days will 18 workers take to complete the same task​

Answers

Answered by Anonymous
1

Answer:

72 days

Step-by-step explanation:

days 15 workrs take to the task = 60

therefore, 1 worker will take = 60/ 15 days to complete the task

= 4

now 18 workers will take= 4 x 18 = 72 days