If 15 workers take 60 days to complete one task how many days will 18 workers take to complete the same task
Answers
Answered by
1
Answer:
72 days
Step-by-step explanation:
days 15 workrs take to the task = 60
therefore, 1 worker will take = 60/ 15 days to complete the task
= 4
now 18 workers will take= 4 x 18 = 72 days