if 15 workers take 8 hours to complete painting how much will 12 workers take to complete the same work
Answers
Answered by
1
Answer:
22.5 hours because 4 person equals to 7.5 hours
Answered by
1
- 15 workers take 8 hours to complete painting.
- Time taken by 12 workers take to complete the same work .
We have given,
15 workers take 8 hours to complete painting.
Hence ,
Using Unitary Method,
15 worker complete a painting in 8 hours
1 worker complete a painting in 8 / 15
12 workers take to complete the same work
➝ 8/15 × 12
➝ 96/15
➝ 6.4 hours
➝ 384 minutes
➝ 6 hrs 24 minutes