If 1500 men can finish a certain construction work in 32 days, how many persons can complete the work in 24 days?
Answers
Answered by
4
Answer: 2000 men
Step-by-step explanation:
= (1500*32) / 24
= (1500*4) / 3
= 500*4
= 2000