IF 16 men can compelete a work in 20 days then in how much days 4 men will do it ?
Answers
Answered by
0
Answer:
Step-by-step explanation:
We will solve this question by using inverse proportion as number of men (x) and number of days (y) are inversely proportion to each other.
We can conclude that,
X x Y = constant
Now,
16 x 20 = 4 x Y
16 x 20/4 = Y
Y = 80
Therefore, 4 men will complete the work in 80 days.