Math, asked by mkowsi1010, 2 months ago

if 16 men can finish a work in 12days,how long will 12 men take to finish the same work.​

Answers

Answered by mahak3922
0

Step-by-step explanation:

formula is X1/X2=y2/y1

16/12=y2/12

16=y2

answer is 16

Answered by typicallyhima
0

Answer:

16 days

Step-by-step explanation:

Attachments:
Similar questions