if 16 men complete a piece of work in 12 days then find the number of men required to complete same work in 4 days​

Answers

Answered by ravikaushikc09
2

Answer:

answer is 48 men

Step-by-step explanation:

given that

16 men= 12 days

? men=4  days

since it is an inverse ratio

(16x12)/4=48 men

HEnce 48 men are required