if 16 men complete a piece of work in 12 days then find the number of men required to complete same work in 4 days
Answers
Answered by
2
Answer:
answer is 48 men
Step-by-step explanation:
given that
16 men= 12 days
? men=4 days
since it is an inverse ratio
(16x12)/4=48 men
HEnce 48 men are required
MArk me as brainliest plz