If 16 men working 7 hours a day can plough a field in 48 days ,how many days will 14 mens working 12 hours a day plogh the same field.
Answers
Answered by
3
Answer:
32 days requires for 14 mens working for 12 hours a day to plough a same field.
Step-by-step explanation: