If 17 labourers can dig a ditch 20 m long in 18 days, working 8 hours a day, how many
more labourers should be engaged to dig a similar ditch 39 m long in 6 days, each
labourer working 9 hours a day?
Answers
Answered by
4
Answer:
this is the answer please mark me as a brainliest
Attachments:
Answered by
0
There will be labourers should be engaged.
Step-by-step explanation:
Since we have given that
If 17 labourers can dig a ditch 20 m long in 18 days, working 8 hours a day,
If dig a similar ditch 39 m long in 6 days, each labourer working 9 hours a day.
According to question, we get that
So, there will be labourers should be engaged.