if 18 men can do a piece of work in 50 days in how many days will 15 men do it?
Answers
Answered by
22
Answer:
=> 18 men can do a piece of work in = 50 days
=> 15 men can do a piece of work in = 50/15 × 18
= 50/5 × 6 (divide by 3)
= 10 × 6 = 60 days.
Step-by-step explanation:
hope it's help you‼️‼️☑️☑️
Answered by
3
Step-by-step explanation:
given, 18 men can do the work in 50 day
1 man can do it in 5O*18 day
15 men can do it in (50/15)18day=60 day