if 18 men can do piece of work in 30 days in how many day will 20 men do it
Answers
Answered by
4
Step-by-step explanation:
18 men can do a piece of work in 30 days
Answered by
19
Answer:
18 men do in 30 days so 1 man will do in 18 into 30 =540 days so 20 men will do 540/20=27 days