if 18 men do a work in 15 days .in how many days will 60 men complete twice the worksmili8822​

Answers

Answered by deepakkumarmahapatra
3

Step-by-step explanation:

total work is = 18*15 = 270

twice work is 540

60 men can do this work in 540/60 = 9 days