Math, asked by ajay496, 1 year ago

if 1800 person can finish the construction of abuilding in 40 days how many persons are needed to complete the construction of the building in 24 days

Answers

Answered by raviravi95
1
so 1080 members are required to complete the work in 24 days
Attachments:
Answered by KeAnil
1
hope u find it helpful
do ask for any clarification
Attachments:

KeAnil: ooh sorry
KeAnil: wt is the right answer
ajay496: ans is 3000
KeAnil: oohl
KeAnil: sorry
ajay496: its ok
KeAnil: btw which class question is this??
ajay496: 8class
KeAnil: ohk
ajay496: please solve my questions