if 1860 person can construct a building in 40 days how many person are needed to construct it in 24 days
Answers
Answered by
2
Answer:3100 workers
Step-by-step explanation:
1860 workers => 40 days
x=> 24 days
1860×40=x×24
(1860×40)/24 =x
x=3100 workers
Answered by
1
Answer:
for 1860 people 40 days
how many people are needed to construct in 24
days
no.of days is inversely proportional to no.of people
1860/x=24/40
1860×40/24=x
x=3100 people
3100 people are needed to construct building in
24 days