If 2 carpenters make a table in 3 days, how many days it will take 3 carpenters to complete the table?

Answers

Answered by ashu4277
20
here's ur answer..........I hope this vl be helpful to u
Attachments:
Answered by VineetaGara
10

The table will be made in 2 days by 3 carpenters

1) This problem is a type of Proportionality and ratio.

2) 2 Carpenters make a table in 3 days

3) 1 Carpenter will make the table in 3*2 = 6 days

4) Hence, 3 Carpenters will make the table in 6/3 = 2 days