If 2 men can finish a job in 10 days, how many men will finish the job in 4 days?
Answers
Answered by
7
Answer:
▶Here's your answer
Men : days
2 : 10
x : 4
▶Let number of men's be x...
⏩Answer is 5 men.
Hope it helps ✌
Answered by
4
Given that :
2 men can Finish the work in 10 days
● If the men will increase then working days will decrease.
◆ If two quantities are related in such a way that increase in one results decrease in other and vice-versa, then it's called Inverse Variation
This is case of inverse variation
Let's consider men be x and days be y
Here,We find a Constant k such that xy = k
Hence,
2 × 10 = x × 4
20 = 4x
x = 20/4
x = 5
5 men will finish job in 4 days